Wednesday, July 9, 2008

SVR Home Progress

Well this is the progress as of July 6th. This is Craig's schedule:



Here is the schedule as of today.




Sub Rough Plumbing July 9th
Backfill July 9th
Pouring Basement & Garage July 10th - 11th
Framing July 14th - 18th
Rough Plumbing July 21st - 23rd
Rough Electrical July 24th - 26th

Now Mom is trying to make all the choices that have to be done.

Fun & Games